WWALS Watershed Coalition, Inc. (WWALS) is Suwannee RIVERKEEPER® WWALS advocates for conservation and stewardship of the surface waters and groundwater of the Suwannee River Basin and Estuary, in south Georgia and north Florida, among them the Withlacoochee, Willacoochee, Alapaha, Little, Santa Fe, and Suwannee River watersheds, through education, awareness, environmental monitoring, and citizen activities.

WWALS
Home

Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15 [Up]

You can help with clean, swimmable, fishable, drinkable, water in the 10,000-square-mile Suwannee River Basin in Florida and Georgia by becoming a WWALS member today!
https://wwals.net/donations/

Pictures

MMM

[Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15]
Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15

[Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15]
Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15

[Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15]
Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15

[Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15]
Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15

[Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15]
Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15

[Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15]
Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15

[Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15]
Consent Order on JEA Buckman Wastewater Treatment Plant --FDEP 2025-09-15

CO-for-toxicity

[Cover letter Enclosure: JEA Buckman Consent Order # 25-1475]
Cover letter Enclosure: JEA Buckman Consent Order # 25-1475
PDF

[OGC FILE NO.: 25-1475]
OGC FILE NO.: 25-1475
PDF

[Table 1: Chronic Whole Effluent Toxicity - IC25]
Table 1: Chronic Whole Effluent Toxicity - IC25
PDF

[Table 2: Aldrin and Total Cyanide]
Table 2: Aldrin and Total Cyanide
PDF

[Table 3: Fecal Coliform, Enterococci, and Ultraviolet Light Dosage]
Table 3: Fecal Coliform, Enterococci, and Ultraviolet Light Dosage
PDF

[Table 4: Total Recoverable Iron, Nickel, Copper, and Total Suspended Solids]
Table 4: Total Recoverable Iron, Nickel, Copper, and Total Suspended Solids
PDF

[ORDERED:]
ORDERED:
PDF

[The facility is currently operating under Toxicity Plan for Correction (PFC) dated July 25, 2022. The PFC outlines steps to correct the toxicity violations. This Toxicity Plan may need to be updated....]
The facility is currently operating under Toxicity Plan for Correction (PFC) dated July 25, 2022. The PFC outlines steps to correct the toxicity violations. This Toxicity Plan may need to be updated....
PDF

[7. Beginning on the first day of the month following the effective date of this Order, and lasting 48 months, the Respondent shall comply with the following WET interim limitations, as shown in Table 5, below:]
7. Beginning on the first day of the month following the effective date of this Order, and lasting 48 months, the Respondent shall comply with the following WET interim limitations, as shown in Table 5, below:
PDF

[Table 5 - WET Interim Limits]
Table 5 - WET Interim Limits
PDF

[10. Within 30 days of the effective date of this Order, Respondent shall pay the Department $24,750.00 in settlement of the regulatory matters addressed in this Order.]
10. Within 30 days of the effective date of this Order, Respondent shall pay the Department $24,750.00 in settlement of the regulatory matters addressed in this Order.
PDF

[13. Respondent agrees to pay the Department stipulated penalties in the amount of $200.00 per day for each and every day Respondent fails to timely comply with any of the requirements of this Order.]
13. Respondent agrees to pay the Department stipulated penalties in the amount of $200.00 per day for each and every day Respondent fails to timely comply with any of the requirements of this Order.
PDF

[This Order is not a settlement of any criminal liabilities which may arise under Florida law, nor is it a settlement of any violation which may be prosecuted criminally or civilly under federal law.]
This Order is not a settlement of any criminal liabilities which may arise under Florida law, nor is it a settlement of any violation which may be prosecuted criminally or civilly under federal law.
PDF

[24. Respondent shall publish the following notice in a newspaper of daily circulation in Duval County, Florida.]
24. Respondent shall publish the following notice in a newspaper of daily circulation in Duval County, Florida.
PDF

[Rules referenced in this Order are available at http://www.dep.state.fl.us/legal/Rules/rulelist.htm]
Rules referenced in this Order are available at http://www.dep.state.fl.us/legal/Rules/rulelist.htm
PDF

[DONE AND ORDERED]
DONE AND ORDERED
PDF

[Exhibit A In-Kind Projects]
Exhibit A In-Kind Projects
PDF

[d. Within 120 days of the effective date of this Consent Order, or, of the Department's notification that applying stipulated penalties to an in-kind project is acceptable Respondent shall obtain approval for an in-kind project from the Department.]
d. Within 120 days of the effective date of this Consent Order, or, of the Department's notification that applying stipulated penalties to an in-kind project is acceptable Respondent shall obtain approval for an in-kind project from the Department.
PDF

[i. If upon review of the notification of completion, the Department determines that the project cannot be accepted due to a substantially incomplete notification of completion or....]
i. If upon review of the notification of completion, the Department determines that the project cannot be accepted due to a substantially incomplete notification of completion or....
PDF

[If the in-kind penalty project is terminated and Respondent timely remits the $24,000.00, no additional penalties shall be assessed under paragraph 13 for failure to complete the requirements of this paragraph.]
If the in-kind penalty project is terminated and Respondent timely remits the $24,000.00, no additional penalties shall be assessed under paragraph 13 for failure to complete the requirements of this paragraph.
PDF