8.2. Watershed Protection Plan (WPP): The permittee did not conduct a Watershed Assessment (WA) nor prepare a Watershed Protection Plan (WPP) as required by the current permit. The City will be required to complete a WA and WPP in accordance with the Notice of Violation transmitted to the City on November 6, 2025.

FS
Reissuance, Quitman WPCP, GAJ020022 --GA-EPD
30 August 2018
 
8.2. Watershed Protection Plan (WPP): The permittee did not conduct a Watershed Assessment (WA) nor prepare a Watershed Protection Plan (WPP) as required by the current permit. The City will be required to complete a WA and WPP in accordance with the Notice of Violation transmitted to the City on November 6, 2025.
bigger PDF